What is the delivery lead time?
- Share
- Issue Time
- Mar 23,2026

Q: What is the delivery lead time?
Standard lead time is 7–15 working days after deposit confirmation for stock models, and 20–35 working days for customized/OEM generator sets. All units undergo a 2-hour no-load + load test before leaving the factory.
🏭 Production & Shipping Flow
- Stock Gensets (Cummins / Perkins / Yuchai standard models): 7–15 working days
- OEM / Private Label (logo + manual + nameplate only): +3–5 working days
- ODM / Technical Customization (voltage, canopy, controller, parallel panel): 20–35 working days
- Container Loading & Export Docs: 2–3 working days after final payment
-
Sea Freight (reference):
- 15–25 days to Africa / Middle East
- 25–35 days to South America
- 30–40 days to Europe
✅ What This Means for You
- Predictable schedule: Clear milestones from deposit to Bill of Lading
- No rush penalty: We do not skip QC to ship faster; every set is load-tested
- Flexible priority: For urgent tenders, we can parallel-source engines to cut 5–7 days (subject to component availability)
- Real-time updates: Photos/videos of assembly, testing, and packing sent at each stage
🌍 Global Shipping Experience
We regularly ship to Nigeria, UAE, Saudi Arabia, Chile, Indonesia, and Turkey, and align lead time with your project commissioning date.
✅ In short: Standard sets ship in 1–2 weeks, custom sets in 3–5 weeks— factory-direct, fully tested, no middleman delay. Tell us your deadline, and we’ll reverse-engineer the production plan to hit it.
For checking suitable generator product for your project — Contact NovArk Power
Get a free power system design consultation for your diesel generator set project. Our engineers will analyze your requirements and deliver a tailored generator solution.
This article is for informational purposes only. Specifications and availability may vary by region. Please contact NovArk Power for a confirmed quotation tailored to your project requirements.